Embedded Processing / High End

MCUs, MPUs, FPGAs, SoCs and high-end logic.

3 · Alert18–44 wksMixed signals: Selected MCU and programmable families are stretching; mainstream parts are steadier.
—
Pulse Indexp20

Lead-time range, Dec 2025 – Oct 2026
Reading the charts

The shaded band is the lead-time range in weeks; the line is its midpoint. A red triangle marks an open-ended “52+” month.

The colored strip shows each month’s status. Gaps are months the category wasn’t reported.

Numbered dots are dated market events. They are listed under the chart on each category page.

03060wksMay 2026: 19–52 wksJun 2026: 19–52 wksJul 2026: 19–52 wksAug 2026: 18–52 wksSep 2026: 18–44 wksOct 2026: 18–44 wks12026-01-15 — US Section 232 tariff: 25% on advanced logic importsDecMarJunSepOct
  1. 1January 15, 2026 — US Section 232 tariff: 25% on advanced logic imports.25% duty on advanced processors above compute/bandwidth thresholds takes effect; pricing pressure and country-of-origin re-engineering.source

Monthly status
Status scale

1 Stable: normal lead times, predictable supply.

2 Watch: early signals such as rising prices or stretching in some families. Monitor.

3 Alert: lead times stretching or selective allocation. Check exposed parts on your BOM.

4 Critical: broad allocation or severe extension. Plan around constraint.

The status is the analyst’s judgment, informed by the sources. It is not a formula.

Full methodology →

Dec 2025: no dataDecJan 2026: 2 · Watch2Feb 2026: 2 · Watch2FebMar 2026: 2 · Watch2Apr 2026: 2 · Watch2AprMay 2026: 3 · Alert3Jun 2026: 3 · Alert3JunJul 2026: 3 · Alert3Aug 2026: 3 · Alert3AugSep 2026: 3 · Alert3Oct 2026: 3 · Alert3Oct

Subcategories, October 2026

SubcategoryStatusLead timeTrendPricingNote
MCUs3 · Alert18–52 wksrisingrising
FPGAs / PLDs3 · Alertnot reportedrisingrising

Month by month

  • Oct 20263 · AlertHigher-end embedded products remain watch-to-alert.
  • Sep 20263 · AlertSelected MCU families at 40 to 52 weeks.
  • Aug 20263 · AlertHigh-end embedded is uneven: specific FPGA, SOM and higher-performance MCU families stretch well past 40 weeks.
  • Jul 20263 · AlertMCU and FPGA watch became alert in May, held into July.
  • Jun 20263 · AlertFPGAs show selected shortages; alert held.
  • May 20263 · AlertEmbedded / FPGA at 19 to 52 weeks; watch became alert in May.
  • Apr 20262 · WatchHigh-end logic under pressure; commodity logic stable.
  • Mar 20262 · WatchDigital categories concentrated pressure; MCU/FPGA watch.
  • Feb 20262 · WatchDiscretes & logic stretching; SMA (selective) pricing increases.
  • Jan 20262 · WatchMCU and FPGA on watch.
Data table
MonthStatusLead timePulse Index
Oct 20263 · Alert18–44 wks—
Sep 20263 · Alert18–44 wks—
Aug 20263 · Alert18–52 wks—
Jul 20263 · Alert19–52 wks—
Jun 20263 · Alert19–52 wks—
May 20263 · Alert19–52 wks—
Apr 20262 · Watch——
Mar 20262 · Watch——
Feb 20262 · Watch——
Jan 20262 · Watch——

Latest reading synthesized from: Future Electronics Market Conditions Report · TTI Lead Time Trends · Sourceability Lead Time Report — see methodology.